OUR GREAT MINDS

by Tina Olivero

Altaley Mining Initiates Mining and Milling Operations

Altaley Mining Corporation (“Altaley” or the “Company”) is excited to announce that the Company has initiated pre-production mining and mill commissioning operations at its Tahuehueto Gold Mine in Durango, Mexico. Construction efforts at the mine site have advanced to allow the startup and commission of one ball mill capable of processing up to 500 TPD.

“I am very excited to see Tahuehueto commencing pre-production activities and look forward with anticipation to our first concentrate deliveries, anticipated in several weeks, which will bring our Company its first revenue from the new, on-site Tahuehueto mineral processing facility” states Ralph Shearing, CEO, “The Tahuehueto gold mine coming on-line is the realization and delivery to shareholders of the Company’s major goal of reaching production on its flagship asset. The robust cash flows anticipated from Tahuehueto should allow us to accelerate our debt repayments; our cash flow modeling suggests all loan debt may be repaid in under two years. We will also re-initiate exploration activities to expand reserves and resources, which exploration I am convinced, can unlock the hidden, undiscovered ultimate potential of this district-scale project allowing mine expansion and extension to the current life of mine.”

Tahuehueto’s processing facility is operational allowing for milling up to 500 tpd with flotation cells, concentrate thickeners and concentrate filters successfully tested and operational.

During the commissioning phase of the first ball mill, a bulk concentrate will be produced, and as soon as possible thereafter, the Company will process a separate precious metal-rich lead concentrate and a zinc concentrate. Copper concentrate production is planned to be initiated in late 2022.

Electrical power generation is being supplied by Aggreko International Power Projects Limited which has installed power generation equipment capable of supplying power to the mining unit for 1,000 tpd sustained production. The water pumping system and the pipeline are operational to supply processing water to the mine at its full planned capacity of 1,000 tpd.

The Company has stockpiled over 29,000 tonnes of ore to be used in the commissioning process and pre-production phases of the 1st ball mill. As soon as the process plant completes its start-up commissioning phase and has been optimized for maximum recoveries and throughput, a higher grade run of mine ore will begin to be processed to maximize revenues during the pre-production phases of the mine.

Altaley’s underground mining contractor has developed access to four stopes, two on the El Creston structure and two on the Perdido structure, providing multiple working faces more than fully capable to supply adequate mill feed for the mine’s start-up 500 tpd phase. Underground development is continuing and will soon provide access to 2 additional stops on Perdido and four additional stops on El Creston at lower elevations and thereby will have complete access to at least 10 mining stopes capable of supplying mill feed to the 1,000 tpd operation upon completion of construction as described below.

The remaining construction to advance the mine to its planned full production capacity of 1,000 tpd is as follows:

2nd Ball Mill installation

Installation of the second 500 tpd ball mill to increase milling capacity to 1000 tpd is planned to be completed in Q3, 2022. Necessary equipment has been acquired, the majority of which is stored on-site or in the Company’s Durango warehouse.

Crushing Circuit

Initial crushing is being handled with a temporary crusher, fully capable of continually feeding the 500 tpd ball mill, while the Company completes construction of the mine’s permanent crushing circuit, which will contain a primary jaw crusher and secondary cone crusher with associated vibrating screens and storage hoppers. All crushing equipment is on-site or in the Company’s Durango warehouse ready for installation. The permanent crushing circuit is approximately 50% complete and expected to be completed during June 2022.

Tailings Thickener and Dewatering

The tailings thickener is functional and tailings filter presses for dewatering are scheduled for installation over the next several weeks to be operational during June 2022. Temporary tailings storage is available to accept pre-production tailings until the formal dry stack tailings storage facility is ready to accept dewatered tailings, which is expected by the end of August 2022.

About Altaley Mining Corporation

Altaley Mining Corporation is a Canadian-based mining company with two 100% owned Mexican gold, silver, and base metal mining projects.

Altaley’s Tahuehueto mining project is in north-western Durango State, Mexico where construction has been advanced to near completion on its 1,000 tonnes per day processing facility and related mine infrastructure to initiate production of gold, silver, lead, and zinc in concentrates at Tahuehueto. The Company is targeting initial pre-production in May 2022 and ramping up to full production capacity during Q3-Q4 2022.

Campo Morado is an operating polymetallic base metal mine with mining and milling equipment currently producing at an average of 2,200 tonnes per day and is currently estimated to be Mexico’s 6th largest zinc producer.

 Visit: www.altaleymining.com

Tina Olivero

    Would you like to know more about this story?

    Let us know who you are and how we can assist you.

    First Name *required

    Last Name

    Company

    Website

    Email *required

    Mobile required

    What are you interested In?

    Learning more about this story?Contacting the company in this story?Marketing for your company?Business Development for your company?

    I am interested in...


    Did you enjoy this article?

    Get Media Kit


    OGM - Our Great Minds